Skip to main content

Lokker Park Playground Renovation 

Completed October 5, 2024

The Lokker Park playground was renovated based on community feedback, capital budget, and District Board of Directors approval.  

Project Status

Phases Date (if applicable) Status
Community Kick Off Meeting Jan. 13, 2024 Completed
Conceptual Plan Presentation Jan. 30, 2024 Completed
Final Concept Presentation Feb. 13, 2024 Completed
Final Concept Approved by Board of Directors May 1, 2024 Completed
Permits  July 25, 2024 Completed 
Demo (demo will be completed in phases)  July 19, 2024  Completed
Build/Construction July 31 - Current Completed
Completion & Grand Opening!  Oct. 5, 2024 Completed

 

Design 

Playground Design Approved by Board of Directors on May 1

 

 

Project Photos (updated with progress)