Springville Dog Park Fence

 We are working toward replacing the wrought iron exterior fence. 

 

Phase Start Date/Month Status
RFP December 2024 In progress for receiving bids
Board Approval March 5, 2025 Board approval on March 5
Construction March 24, 2025 Completed April 28, 2025

 